Nec 300 5 underground wiring conduits and raceways direct buried cable or conduit or other raceways shall meet the following minimum cover requirements.
Underground service entrance cable requirements.
5trenches to be in as straight and direct a line as possible.
14 2 wg 14 gauge 2 conductors with ground etc.
Al aluminum conductor.
Current transformer cabinets overhead or underground service window type ct s figure 11.
For service entrances of 201 to 400 amperes as determined by the nameplate ampacity of the service disconnect a rain tight current transformer enclosure constructed of code gauge metal with an approved mounting base for bar type current transformers shall be used.
At 18 inches you can use thwn 2 conductors inside a continuous length of pvc conduit which protects the wire all the way through the trench to the house.
Type se or service entrance cable having a flame retardant moisture resistant covering or type use which is service entrance cable identified for underground use having a moisture resistant covering but not required to have a flame retardant covering.
According to 338 2 there are two types of service entrance cables.
A disconnecting means must be provided for all.
How to translate the electrical wire markings on nmc cable.
Service entrance disconnect and location shall conform to the latest version of the nec and all local ordinances.
Any conduit crossing under a road shall be schedule 80.
14 2 14 gauge 2 conductors etc.
For overhead service weather head must be a minimum of three feet above the roof.
Single mobile home underground service pressure treated post figure 9a.
4conduit minimum depth 36 inches.
Requirements for nonmetallic conduits nonmetallic conduits or raceways approved for buried cable give less protection than metal conduits and require greater burial depths.
Meter base mounted on exterior wall of house or mobile manufactured home.
Cu copper.
Single phase underground service meter installation figure 9.
Minimum 6 copper ground wire securely stapled to wall.
Conduits installed less than 36 inches in depth require cooperative engineering approval and shall beencased in concrete to cooperative specs depths specified are to finished grade.
12 2 12 gauge 2 conductors.
At 24 inches you can bury underground feeder cable using pvc conduit to 18 inches below ground only where the wire comes up.
Single mobile home underground service alternate meter pedestal figure 10.
For underground service the poured footing must be notched out for the conduit.